Bathla Collapse Leaves Sydney Housing Developments Stalled and Communities Waiting

Nov 08, 2026 · 327 views

Hundreds of Bathla projects remain unfinished as replacement builders weigh risks, leaving buyers waiting and raising concerns about neglected sites and property values.

Bathla Collapse Leaves Sydney Housing Developments Stalled and Communities Waiting

Some of Bathla’s unfinished Sydney developments risk becoming “wastelands”, expert warns

The risk from Bathla Group’s collapse reaches beyond incomplete houses. If stalled construction drags on, residents could face neglected sites, weaker property values and communities left waiting for homes that were meant to bring them together.

Rinnah Roque and Margarita Elizan stand in the garden of their home with a construction site across the road.
Rinnah Roque (left) and her mother’s home is across the road from an unfinished Bathla housing development. (ABC News: Tony Ibrahim)

Rinnah Roque, 60, bought a three-storey townhouse off the plan in Box Hill, in Sydney’s north-west, hoping to build a home for herself and her mother in a growing community. Across Hynds Road, Bathla was building 47 homes. Now the work has been silent for two months.

“I worked so hard to be able to buy a property for my mum and myself,” Roque said. She had hoped the houses would go up quickly: “You want to live in a community.”

Unfinished development on Hynds Road in Box Hill.
Construction on Hynds Road stopped after Bathla entered administration. (ABC News: Tony Ibrahim)

“All of a sudden everything stopped,” she said. “What’s so frustrating is everything was just left behind.”

The Box Hill project is one of hundreds caught in Bathla Group’s $3.4 billion collapse, with dozens of developments part-built when funding dried up. Some private equity firms owed money by Bathla have taken control of projects they financed and are trying to find builders to complete them. That search may take time: experts and industry stakeholders say replacement builders could be wary of taking responsibility for work they didn’t do.

Margarita Elizan stands on her balcony overlooking an unfinished housing development.
The Box Hill development is among hundreds affected by Bathla Group’s collapse. (ABC News: Tony Ibrahim)

Bathla declined the ABC’s requests for an interview and comment.

Why finishing the projects may be difficult

The obstacle isn’t only finding a builder. A new contractor may struggle to judge whether existing work is sound, and could be asked to warrant construction completed by someone else, said Lyndall Bryant, a property economics professor at Queensland University of Technology.

“If you’re a builder coming into a job that’s half-finished, you don’t want to be warranting the work that someone else has done,” she said. “If the concrete’s been poured, you don’t want to be saying, ‘Oh yeah, I guarantee that that concrete’s been done properly.’”

Lyndall Bryant sits behind a desk inside an office.
Lyndall Bryant says builders may hesitate to take on half-finished projects. (ABC News: Aisling Brennan)

Checking plumbing or electrical work can be especially hard once walls are up. A private equity firm that spoke to the ABC anonymously said builders it had approached were cautious, but it remained confident it would appoint one.

Urban Taskforce Australia, which represents developers and equity financiers, expects most projects to be completed. Its chief executive, Tom Forrest, said he would worry if serious defects cost more to fix than the approved land was worth, though he couldn’t see that happening across many sites.

The costs of Bathla’s collapse could extend beyond stranded buyers. If local councils have to finish roads and sewerage that Bathla was expected to provide, ratepayers could end up funding infrastructure for developments that serve relatively few people. Professor Bryant warned that Blacktown City Council could face significant costs while also losing the rates revenue it expected from completed homes. Mr Forrest said delays would disrupt the council’s cash flow. Blacktown Council declined to comment. The Hills Shire Council Mayor, Michelle Byrnes, called the collapse “another hit to public confidence in the construction industry.” She said she was devastated for Sydney buyers left stranded by Bathla.
Michelle Byrne, with blonde hair, wearing a pin-striped jacket, smiles near a memorial.

Michelle Byrne says the public's confidence in the construction industry has been dealt another blow. (ABC News: Declan Bowring)

Private equity investors race to recoup investments

For investors holding Bathla sites, the immediate priority is getting construction moving again. Some have taken control of their projects and are trying to finish them; one investor said breaking even would be the goal, with any profit a bonus. PAG, an Asian private equity firm, has appointed ParkView to build its 300-unit development at Pemulwuy. Ray White Capital, which owns the Box Hill site, expects its project to be complete before April 2027. Leda Group has taken over a 240-unit development in Marsden Park and says it is in advanced talks with a builder. Other private equity firms told the ABC they were still in discussions with builders. That recovery effort won’t cover every site. A 49-home estate at Lochinvar, in the NSW Hunter Region, has not been taken over by a creditor. Restructuring and insolvency firm Mackay Goodwin has been appointed to “assess available options”. For buyers and councils, the difference between a site with a replacement builder and one still under review could mean a long wait before the full cost of Bathla’s collapse becomes clear.
Source: Tony Ibrahim · www.abc.net.au